Rehabilitation of Acquired-Land Owners and RAJUK’s Duty to Allot Plots: A Case Comment on Most. Taslima Akter v. Government of Bangladesh and others, Writ Petition No. 3712 of 2014
Rehabilitation of Acquired-Land
Owners and RAJUK’s Duty to Allot Plots: A Case Comment on Most. Taslima Akter v. Government of Bangladesh and others, Writ
Petition No. 3712 of 2014
Abstract
This decision of the High Court Division addresses a
recurring problem in land acquisition and rehabilitation: whether an affected
landowner may be denied allotment of a rehabilitation plot merely because part
of the compensation award was issued after the original application date. The
Court held that RAJUK acted unlawfully in rejecting the petitioner’s claim on
that ground and directed allotment of a 3-katha plot within three months. The judgment is significant for new judges,
advocates, judicial service candidates, and legal academics because it
clarifies the relationship among administrative fairness, legitimate treatment
of affected persons, Article 27 and 31 concerns raised in the pleadings,
Section 42 of the Town Improvement Act, and the public duty of rehabilitation
in development projects.
1.
Case Identification
Case: Most. Taslima Akter v. The Government of
Bangladesh and others
Court: High Court Division, Supreme
Court of Bangladesh
Bench: Mr. Justice Bhishmadev
Chakrabortty and Mr. Justice Murad-A-Mowla Sohel
Case No.: Writ Petition No. 3712 of
2014
Date of Judgment: 02.03.2026
2.
Why This Case Matters
The judgment is important because it emphasizes that
an acquiring/development authority cannot rely on its own delay in payment of
compensation or issuance of award certificate to defeat the rehabilitation
claim of an affected person. It also reinforces that displaced persons should
be rehabilitated first in a development project and that acquisition for
residential purposes without accommodating affected persons cannot truly serve
public interest.
3.
Facts of the Case
The petitioner was owner and possessor of lands in
Baunia and Deul mouzas under Savar Police Station, District Dhaka. The
Government acquired her land for RAJUK through LA Case No. 06/2001-2002. The
acquired land measured .0996 acres in Baunia mouza and .0960 acres in Deul
mouza, totaling .1956 acres.
The petitioner received compensation award for the
Baunia land on 07.02.2004 and for the Deul land on 07.03.2005. RAJUK
published a notice in the Daily Ittefaq
on 01.01.2004 inviting applications from affected persons for allotment of
3-katha and 5-katha plots in the 3rd phase of the extended project.
After depositing Tk. 75,000, the petitioner applied for
a 3-katha plot. Her application bore No. 28349 and was filed on 30.03.2004.
At the time of application, she had only the award relating to the Baunia
land; the award for the Deul land had not yet been given. She later sought to
add the award certificate for the Deul land to her original application.
When the list of successful allottees was published on
06.10.2006, her name did not appear. She made multiple representations in 2008,
2009, and 2013. She also earlier filed Writ Petition No. 6979 of 2013 seeking a
direction for allotment, and the Court directed respondents 2 and 3 to dispose
of her application within a specified time. Thereafter, RAJUK communicated that there was
no scope to consider applications where additional awards had been added later
for more lands.
4.
Procedural History
The present Rule was issued challenging the memo dated
07.01.2014 refusing to allot a plot to the petitioner as an affected person and
also challenging the relevant clause contained in memo dated 05.07.2012. The petitioner also sought a direction upon
the respondents to allot her a 3-katha plot on the basis of application No.
28349.
RAJUK contested the Rule by affidavit-in-opposition,
asserting that the petitioner originally applied with award for only .0996
acres, which was below the threshold, and that later-added land could not be
counted because the number of such applications exceeded available plots. In
a supplementary affidavit, RAJUK further stated that out of 2,199 plots
reserved for affected persons, 2,104 had already been allotted, and the
remaining 95 plots were to be allotted pursuant to a meeting dated 13.07.2023;
it also claimed that the petitioner had filed a fresh application on 23.11.2023
which remained pending.
5.
Issues Before the Court
The judgment raises the following core issues:
1. Whether
RAJUK lawfully rejected the petitioner’s application on the ground that she
added a later-issued award certificate after her original application.
2. Whether
the petitioner could be deprived of allotment because part of the compensation
award was issued after the application date due to the authority’s own delay.
3. Whether
the writ petition remained maintainable despite the petitioner’s later fresh
application filed in 2023.
4. Whether
RAJUK, under its statutory and public obligations, was required to prioritize
rehabilitation of displaced persons.
6.
Arguments of the Parties
A.
Petitioner’s Submissions
The petitioner argued that her total acquired land was
.1956 acres, which satisfied the minimum land requirement once both awards were
considered. She contended that she could not submit the Deul mouza
award with the original application because that award was issued only on
07.03.2005, after the application was filed on 30.03.2004. She also
argued that RAJUK accepted the later addition of the award certificate and that
RAJUK’s own board had decided to allot 3-katha plots to affected persons whose
acquired land measured at least .165 acres.
The petitioner relied on Rajdhani Unnayan Kartipaksha
(RAJUK) vs. Mrs. Jahanara Begum and others, 57 DLR (AD) 80 = 25 BLD (AD) 149 =
12 BLT (AD) 222, Rabiul Husain vs. Government of the Bangladesh, 12 ALR (HCD)
50, and Firoza Khatun alias Firoza and others vs. Government of Bangladesh and
others, 30 BLC 362.
B.
RAJUK’s Submissions
RAJUK argued that the petitioner originally applied on
the basis of only .0996 acres, which fell below the eligibility requirement,
and that applications becoming qualified only through later-added awards could
not be considered. It also submitted that there was scarcity of
plots and that the petitioner’s fresh application in 2023 made the earlier
cause of action obsolete.
RAJUK relied on Rajdhani Unnayan Kartipaksha and
another vs. Dr. Tofail Hoque and another 27 BLC (AD) 91 for the proposition
that where no legal and vested right has accrued, no mandamus should issue.
7.
Findings of the Court
The Court found several facts to be admitted by RAJUK:
· the
petitioner’s lands in Baunia and Deul mouzas were acquired through the LA case;
· compensation
for .0996 acres was given on 07.02.2004 and compensation for .0960 acres was
given on 07.03.2005;
· the
petitioner filed application No. 28349 on 30.03.2004 after depositing Tk.
75,000;
· RAJUK
did not deny that the petitioner later filed an application adding the award
certificate for the Deul mouza land.
The Court also found that RAJUK’s Board Meetings dated
23.09.2010 and 26.09.2010 decided to allocate plots to those persons from whom
.1650 acres or more nal land had been
acquired. In the Court’s view, the later rejection of the petitioner’s claim on
the ground of subsequent addition of award certificate was contrary to RAJUK’s
earlier decision and to the advertisement conditions applicable to affected
persons.
Most importantly, the Court held that the petitioner
could not be deprived of a plot due to the respondents’ own fault in delayed
payment of compensation and delayed issuance of award certificate.
8.
Maintainability and the 2023 Fresh Application
The Court rejected RAJUK’s argument that the fresh
application filed in 2023 extinguished the cause of action in the writ
petition. It observed that the petitioner had first applied in 2004, had waited
for years, had made several representations, and had already obtained a prior
court direction in 2013, but RAJUK still rejected her claim on what the Court
regarded as a flimsy ground.
The Court criticized RAJUK’s conduct as dilatory and
stated that such tactics could not be allowed to continue.
9.
Distinction from the Case Relied on by RAJUK
The Court held that Rajdhani Unnayan Kartipaksha and
another vs. Dr. Tofail Hoque and another 27 BLC (AD) 91 did not apply to the
present facts. According to the judgment, that case involved a newspaper
publication showing allotment followed by cancellation on grounds of
irregularity and illegality, and the writ there was purely in the nature of
mandamus; by contrast, the present Rule was in a mixed form of certiorari and
mandamus challenging an actual rejection order.
10.
Statutory Principle: Section 42 of the Town Improvement Act
The Court expressly referred to Section 42 of the Town
Improvement Act and stated that it provides for re-housing persons displaced by
an improvement scheme. The Court further stated that RAJUK’s prime duty is to
rehabilitate displaced people first and then accommodate others. This is one of
the most important doctrinal features of the judgment.
11.
Ratio Decidendi
The ratio of the case may be stated as follows:
Where
land is acquired for a development project and the affected person’s total
acquired land satisfies the authority’s eligibility threshold, the authority
cannot lawfully reject the claim for rehabilitation allotment merely because
part of the compensation award was issued after the original application date,
especially where such delay is attributable to the authority itself.
A second principle also emerges:
In
schemes involving acquisition for residential development, rehabilitation of
displaced persons is a priority public duty, and administrative action
inconsistent with that duty may be struck down.
12.
Final Order
The Rule was made absolute. The Court declared the
memo dated 07.01.2014 and the relevant clause of memo dated 05.07.2012 to have
been made without lawful authority and to be of no legal effect. RAJUK was
directed to allot a 3-katha plot to the petitioner as an affected person in
accordance with law on the basis of her application dated 30.03.2004 bearing
No. 28349 within three months from receipt of the judgment and order.
13.
Lessons for Judges, Lawyers, and Judicial Service Candidates
A.
For Judges
This case shows the importance of testing
administrative decisions for internal inconsistency, arbitrariness, delay, and
unfairness.
B.
For Advocates
The case illustrates effective use of:
· admitted
facts;
· earlier
board decisions of the authority;
· prior
writ history and non-compliance with court directions;
· statutory
policy under Section 42 of the Town Improvement Act.
C.
For BJS Examination Candidates
This is a strong authority on:
· writ
jurisdiction in mixed certiorari-mandamus form;
· administrative
arbitrariness;
· rehabilitation
of displaced persons in acquisition matters;
· the
legal effect of self-contradictory administrative decisions.
D.
For Teachers and Students
The judgment is useful for classroom discussion on
fairness in public administration, acquisition and rehabilitation, legitimate
state conduct, and judicial control of statutory authorities.
14.
Concluding Evaluation
This judgment stands as a notable reaffirmation that
development authorities must act fairly, consistently, and in accordance with
their rehabilitation obligations. A person whose land has been acquired cannot
be disqualified because the authority itself delayed the award process. The
Court’s intervention protects not only the petitioner’s claim, but also the
broader rule-of-law principle that public bodies may not defeat substantive
rights through procedural unfairness or administrative delay.

Comments
Post a Comment